This project was to redevelop an existing MRI & CT suite within a live hospital. This consisted of a new layout adding a Disabled WC, 1No Changing Room, 1No Disabled Change and a new Bed Prep Area. A New RF Cage including steel shielding to the rear wall and additional lead works to the CT Exam Room.
The construction works included the following:-
Strip out of all areas to be redeveloped
Lead lining as instructed by the RPA
Construction of partition walls to form new layout
Joinery works
M&E modifications and upgrades, including a new AHU and plant area