Programme Length:

Project Value:

Project Description:

3 Weeks

£122,000.00

Office Fit Out

This project involved converting 5 nr small managed offices located on the 1st floor of an office block into one large office space. The challenge with this scheme was the short timescales, we had a very minimum lead in time and just 3 weeks on site. Handover over was then very shortly after during the Christmas period. All was completed to a very high standard despite the tight schedule.

The construction works included the following:-

  • Strip out of all finishes.
  • Removal of partition walls
  • Completion of a glass wall to form the Meeting Room
  • Completion of a new Data Room.
  • Form a Kitchen / Staff Area
  • Small Power and Lighting Works
  • Mechanical works
  • Fitted Furniture