Rotherham General Hospital

Project Description:

Programme Length:

Project Value:

MRI Scanner

18 weeks

£1,300,000.00

Overview

This project was a design & build refurbishment of an existing Angiography Room / Area, undertaken whilst retaining continued use of the second MRI suite/rest of the facility.

The works included the following:

  • Removal of redundant fixtures & fittings; retain other items as instructed by end user
  • Full internal demolition works
  • Full internal fit out
  • New RF cage
  • Structural works associated with M&E installation
  • New plant deck/AHU pod installed on flat roof area
  • New mains supply cable
  • Upgrade electrical installation to suit new equipment and meet current regulations
  • New Joinery/fitted furniture package
  • New vinyl floor install throughout
  • Decoration
  • Crane lift for all plant onto flat roof area

All works have been designed and compliant in the most up to date HTM guidelines and all statutory requirements.