MONTGOMERY PRIMARY SCHOOL
Programme Length:
Project Value:
Project Description:
22 Weeks
£330,000.00
Extension and Refurbishment
This project was for the construction of a new extension to form a new library area including refurbishment of existing areas of the school. The main construction works were completed during the school holidays, with the internal fit out and refurbishments being complete during the autumn term time.
The construction works carried out included the following:
Part demolition and groundwork’s for new extension
New superstructure including curtain walling / structural glazing
Single ply roof coverings
Aluminium Rainwater Goods
Internal walls, partitions and ceiling finishes
Toilet refurbishment & formation of new reception areas
Bespoke fitted furniture
M&E installations
External hard and soft landscaping