Project Description:

Programme Length:

Project Value:

Nuclear Medicine

12 Weeks

£290,000.00

 

This project was to redevelop an existing CT and bed prep area within a live hospital. This consisted of the enlargement of the existing Exam Room, incorporating new RPA lead works , new Lead doors with integral warning lights to enable the installation of a new Siemens Spec CT. We also created a new Control Room and Argus Room to improve the new Nuclear Medicine Department.

The construction works included the following:-

  • Strip out of all areas to be redeveloped
  • Lead lining as instructed by the RPA
  • Construction of partition walls to form new layout
  • Joinery works
  • M&E modifications and upgrades
  • Internal finishes
  • Fitted furniture