Siemens Healthineers

Kent & Canterbury Hospital

Project Description:

Programme Length:

Project Value:

IR Suite

42 Weeks

£1,930,000.00

This design and build project was awarded under the turnkey scheme in association with Siemens Healthineers, the scheme consisted of remodelling an existing X-Ray Department into a new IR suite containing an ARTIS Pheno Interventional Angiography System. The team worked closely with the East Kent Hospitals University NHS Foundation Trust, overcame many challenges to complete the works, including a 500t crane lift of a new HTM compliant Air Handling Unit onto the existing roof. This is the first phase of three planned by the Trust which will enhance the hospital’s capabilities.

The construction works included the following:-

  • Strip out of all areas to be redeveloped
  • Installation of new structural steelwork
  • M&E Installation
  • Medical Gases
  • Radiation Protection in line with RPA requirements
  • Internal Fit Out
  • Joinery and Fitted Furniture

All works were designed and compliant to HTM guidelines and all statuary requirements.