Programme Length:
Project Value:
Project Description:
10 Weeks
£327,500.00
Linac Bunker Refurbishment
This scheme involved the strip out, remodeling and refurbishment of an existing basement areas within a live hospital, including ancillary office, to create a new Linac Accelerator treatment area.
The site itself was extremely limited so there was great emphasis on material movements and storage as well and close co-ordination with the site facilities team to manage services shut downs and isolations.
The construction works included the following:-
- Internal Partitions
- Mechanical and Electrical Installations
- Internal Doors
- Wall Protection
- New wall, floor and ceiling finishes
- Bespoke fitted furniture
- Drainage Alterations
- Replacement Sanitary ware
![IMG_5081](https://mogroup.uk/wp-content/uploads/2019/10/IMG_5081-570x450.jpg)
![IMG_5012](https://mogroup.uk/wp-content/uploads/2019/10/IMG_5012-570x450.jpg)
![IMG_5024](https://mogroup.uk/wp-content/uploads/2019/10/IMG_5024-570x450.jpg)
![IMG_5030](https://mogroup.uk/wp-content/uploads/2019/10/IMG_5030-570x450.jpg)
![IMG_5036](https://mogroup.uk/wp-content/uploads/2019/10/IMG_5036-570x450.jpg)
![IMG_5066](https://mogroup.uk/wp-content/uploads/2019/10/IMG_5066-570x450.jpg)
![IMG_5150](https://mogroup.uk/wp-content/uploads/2019/10/IMG_5150-1-570x450.jpg)
![IMG_5009](https://mogroup.uk/wp-content/uploads/2019/10/IMG_5009-570x450.jpg)