Eltham Community Centre
Community Diagnostic Centre
Project Description:
Programme Length:
Project Value:
Community Diagnostic Centre
40 Weeks
£3,065,000.00
This project involved the alterations, refurbishment and specialist fit out of the existing Eltham Community Centre to facilitate the installation of new medical imaging equipment, to provide MRI, CT, ultrasound and X-ray scanning services.
In addition to the main equipment rooms, offices, consulting rooms, waiting areas, staff welfare and changing rooms and a refurbished reception areas were also created
The construction works included the following:-
- Installation of internal partitions
- Alterations to fire strategy
- Code 5 & 6 lead protection and specialist fit out for CT and X-ray installation
- RF Cage and specialist fit-out for MRI installation
- Extensive M&E installation
- Specialist fit-out for exam room installations
- High end clinical finishes to all areas, including feature walls and recessed lighting