INHEALTH
Croydon University Hospital
Project Description:
Programme Length:
Project Value:
3 Nr MRI Scanners
35 Weeks
£1,700,000.00
This scheme was secured under a negotiated open book & consisted of the total redevelopment of an existing MRI suite, with an additional area added so that a 3rd MRI could be installed. The project was phased with the need to deliver and get the 3rd MRI installed and operational before the existing 2 could be removed. The Logistics had to be carefully considered to minimise disruption to the surrounding departments.
The construction works included the following:-
- Strip out of all areas to be redeveloped
- Steel shielding & RF Cabin works
- Construction of partition walls to form new layout
- Joinery works
- Extensive M&E works
- Internal finishes
- Fitted furniture
- External plant deck
- Underground drainage works