SPIRE HEALTHCARE

Harpenden

Programme Length:

Project Value:

Project Description:

24 Weeks

£1,596,00.00

Modular Theatre

This project was a pre designed competitive tender. All works were within a live private Hospital and had to be split into 3 phases over 26 weeks to enable the Hospital to remain functional during the construction period.

 

The construction works included the following:-

 

  • Groundworks and drainage alterations

  • Ground floor slab to receive modular building

  • Creation of new Wellness Suite below new modular building

  • Refurbishment of existing office and consulting rooms

  • Alterations and refurbishment of existing bedroom, recovery areas and operation theatres