Royal Derby Hospital

Programme Length:

Project Value:

Project Description:

13 Weeks

£263,00.00

Linac Bunker 1 & 2

This project was a D&B turnkey scheme and the works included the remodelling and refresh of an existing Linac Bunker to facility the refurbishment of an existing Linac Accelerator.  

The construction works included the following:-

  • Removal of redundant fixtures and fittings

  • Installation of new Varian pit to accommodate base plate requirements

  • Ductwork modifications to suit equipment supplies

  • Replacement floor and ceiling finishes

  • Decorations

  • Fixture and fittings

  • M&E Alterations to suit new layout