Programme Length:

Project Value:

Project Description

37 Weeks

£511,912.94

4nr Cath Labs & Recovery

This project was a D&B turnkey scheme for the creation of 4nr new Cath Labs and a Recovery area within an existing hospital area, all carried out on a Phased arrangement whilst maintaining day-today hospital operations. The project also involved the supply and installation of a complete new IPS/UPS system and UPS configuration for all small power and lighting within the Cath Labs and Recovery area, with the electrical infrastructure being re-modelled to facilitate the scheme.  

The electrical works carried out included the following:

    • A fully designed electrical system

    • Electrical isolations using company LOTO procedure

    • Alterations to the existing electrical infrastructure

    • Removal of all redundant electrical fixtures and fittings

    • Upgrades to existing panel boards

    • Strip out of existing finishes

    • Installation of a fully compliant HTM 06-01 IPS/UPS system

    • Dedicated distribution boards for mechanical plant, IPS/UPS, small power and lighting

    • Complete new earthing system within the Cath Lab and recovery area

    • LED lighting system including colour changing perimeter lighting

    • Fully UPS backed distribution network for with dedicated distribution boards for each lab

    • Fire alarm and nurse call alterations

    • Lighting protection and surge protections works

Registered Address: Park House, 37 Clarence Street, Leicestershire, LE1 3RW

Company Registration Number: 07203361

VAT Reg No. GB 102 9938 13

© 2019 M&O Electrical Ltd. All rights reserved. | Web design by Ted Press