ROYAL BOURNEMOUTH HOSPITAL
Programme Length:
Project Value:
Project Description
37 Weeks
£511,912.94
4nr Cath Labs & Recovery
This project was a D&B turnkey scheme for the creation of 4nr new Cath Labs and a Recovery area within an existing hospital area, all carried out on a Phased arrangement whilst maintaining day-today hospital operations. The project also involved the supply and installation of a complete new IPS/UPS system and UPS configuration for all small power and lighting within the Cath Labs and Recovery area, with the electrical infrastructure being re-modelled to facilitate the scheme.
The electrical works carried out included the following:
A fully designed electrical system
Electrical isolations using company LOTO procedure
Alterations to the existing electrical infrastructure
Removal of all redundant electrical fixtures and fittings
Upgrades to existing panel boards
Strip out of existing finishes
Installation of a fully compliant HTM 06-01 IPS/UPS system
Dedicated distribution boards for mechanical plant, IPS/UPS, small power and lighting
Complete new earthing system within the Cath Lab and recovery area
LED lighting system including colour changing perimeter lighting
Fully UPS backed distribution network for with dedicated distribution boards for each lab
Fire alarm and nurse call alterations
Lighting protection and surge protections works
Registered Address: Park House, 37 Clarence Street, Leicestershire, LE1 3RW
Company Registration Number: 07203361
VAT Reg No. GB 102 9938 13
© 2019 M&O Electrical Ltd. All rights reserved. | Web design by Ted Press