InHealth

East Surrey Hospital

Programme Length:

Project Value:

Project Description:

30 Weeks

£1,412,000.00

SaSH Dual MRI

This project was pre-designed and was secured via competitive tender, the scope of works consisted of constructing a single storey extension which linked 2 buildings together to create a larger MRI suite and form an additional MRI Examination Room, along with extensive remodelling and upgrading works to the existing MRI suite.  to minimise downtime of the existing MRI we split the works into 2 phases over a total of 30 weeks.

The construction works included the following –

  • Groundworks and drainage alterations

  • Construction of a single storey building

  • Extensive remodelling and refurbishment works

  • Extensive M&E works

  • High level finishing works